cluster:178 [2019/08/16 13:01] hmeij07 [Tech Summary] |
cluster:178 [2019/08/20 11:46] hmeij07 [Aug Meetings] |
||
---|---|---|---|
Line 44: | Line 44: | ||
^ Proposed Excley Data Center Loads ^ total kW ^ | ^ Proposed Excley Data Center Loads ^ total kW ^ | ||
- | | Emergency power backed racks| | + | | Emergency power backed racks (x2)| 43.5| |
| HPC Racks| | | HPC Racks| | ||
| Storage (rstore)| | | Storage (rstore)| | ||
Line 187: | Line 187: | ||
Cancelled | Cancelled | ||
+ | |||
+ | **8/20** | ||
+ | |||
+ | Meetings moved to Thu afternoon (1pm now vs 7:30am) | ||
+ | New CRAC2 unit on, data center temp dropped 5-7 degrees | ||
+ | Modular wall up | ||
+ | Fire suppressant install next, followed by ceiling | ||
+ | Reconfigure floor tiles near CRAC2 | ||
+ | Old CRAC1 demolishing started | ||
+ | |||
===== Aug Photos ===== | ===== Aug Photos ===== |