**Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | **Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | ||
- | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. | + | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. |
* Project Schedule: 5/28/19 – 10/1/2019 | * Project Schedule: 5/28/19 – 10/1/2019 | ||
Line 17: | Line 17: | ||
The HPCC is in the top row of racks on the left (room for 3 additional racks, light yellow dots, 5 existing racks, dark yellow dots). | The HPCC is in the top row of racks on the left (room for 3 additional racks, light yellow dots, 5 existing racks, dark yellow dots). | ||
+ | ===== Summary Bullets ===== | ||
+ | |||
+ | ⦁ Replace computer room air conditioning units (CRAC, Liebert DSE DA085)\\ | ||
+ | ⦁ Replace rooftop condensing units\\ | ||
+ | ⦁ Install new economizers and pump packages\\ | ||
+ | ⦁ Install new drop ceiling and lighting (LED) with dim switch\\ | ||
+ | ⦁ R-410A refrigerant, | ||
+ | ⦁ Reduce | ||
+ | ⦁ Install hot and cold isle containment system (vinyl curtains)\\ | ||
+ | ⦁ Abandon sub floor cold air delivery (push cold air above floor)\\ | ||
+ | ⦁ Total load of approx 88 Kw (~20% growth, 45 Kw for ITS, 25 Kw for HPCC)\\ | ||
+ | ⦁ Save approx 260,000 Kwh/yr of electricity (estimated at $35,000 /yr in savings)\\ | ||
+ | ⦁ ROI of 7-8 years\\ | ||
+ | |||
+ | [[https:// | ||
===== Tech Summary ===== | ===== Tech Summary ===== | ||
Line 190: | Line 205: | ||
**8/20** | **8/20** | ||
- | Meetings moved to Thu afternoon (1pm now vs 7:30am) | + | Meetings moved to Thu afternoon (1pm now vs 7:30am)\\ |
- | New CRAC2 unit on, data center temp dropped 5-7 degrees | + | New CRAC2 unit on, data center temp dropped 5-7 degrees\\ |
- | Modular wall up | + | Modular wall up\\ |
- | Fire suppressant install next, followed by ceiling | + | Fire suppressant install next, followed by ceiling\\ |
- | Reconfigure floor tiles near CRAC2 | + | Old CRAC1 demolishing started\\ |
- | Old CRAC1 demolishing started | + | |
+ | **08/22** | ||
+ | |||
+ | Wall AC units on\\ | ||
+ | Dim switch relocated, network area missing led installed\\ | ||
+ | Old CRAC1 removed\\ | ||
+ | Floor tiles slowly reconfigure, | ||
+ | Condenser leak in second unit, new item shipped\\ | ||
+ | Deliver new CRACR1 before move in day\\ | ||
+ | Fire suppression wiring and piping today\\ | ||
Line 214: | Line 238: | ||
{{: | {{: | ||
{{: | {{: | ||
- | {{: | + | {{: |
{{: | {{: | ||
{{: | {{: | ||
- | {{:cluster:100_2387_small.jpg? | + | {{:cluster:pp-crac2-small.jpg? |
+ | {{: | ||
+ | {{: | ||
+ | |||
+ | ===== Sept Meetings ===== | ||
+ | |||
+ | **09/05** | ||
+ | |||
+ | New electrician but critical work coming up\\ | ||
+ | Missing one track sensor\\ | ||
+ | CARC1 installed, piping finish and leak test\\ | ||
+ | New CRAC1 power up 9/19 by Liebert with owner training\\ | ||
+ | Duct work and dampers install today\\ | ||
+ | |||
+ | **09/19** | ||
+ | |||
+ | Cancelled | ||
+ | |||
+ | ===== Sept Photos ===== | ||
+ | |||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | |||
+ | |||
+ | ===== The End ===== | ||
+ | |||
+ | Working with PP to see if we can do a floor tile cleaning. | ||
+ | Scroll up for the whole story backwards. | ||
- | \\ | ||