cluster:178 [2019/08/20 12:40] hmeij07 [Aug Photos] |
cluster:178 [2019/08/22 17:59] hmeij07 [Aug Photos] |
||
---|---|---|---|
Line 190: | Line 190: | ||
**8/20** | **8/20** | ||
- | Meetings moved to Thu afternoon (1pm now vs 7:30am) | + | Meetings moved to Thu afternoon (1pm now vs 7:30am)\\ |
- | New CRAC2 unit on, data center temp dropped 5-7 degrees | + | New CRAC2 unit on, data center temp dropped 5-7 degrees\\ |
- | Modular wall up | + | Modular wall up\\ |
- | Fire suppressant install next, followed by ceiling | + | Fire suppressant install next, followed by ceiling\\ |
- | Reconfigure floor tiles near CRAC2 | + | Old CRAC1 demolishing started\\ |
- | Old CRAC1 demolishing started | + | |
+ | **08/22** | ||
+ | |||
+ | Wall AC units on\\ | ||
+ | Dim switch relocated, network area missing led installed\\ | ||
+ | Old CRAC1 removed\\ | ||
+ | Floor tiles slowly reconfigure, | ||
+ | Condenser leak in second unit, new item shipped\\ | ||
+ | Deliver new CRACR1 before move in day\\ | ||
+ | Fire suppression wiring and piping today\\ | ||
Line 217: | Line 226: | ||
{{: | {{: | ||
{{: | {{: | ||
- | {{:cluster:100_2387_small.jpg? | + | {{:cluster:pp-crac2-small.jpg? |
+ | {{: | ||
+ | {{: | ||
- | \\ | ||
**[[cluster: | **[[cluster: |