**Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | **Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | ||
- | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. | + | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. |
* Project Schedule: 5/28/19 – 10/1/2019 | * Project Schedule: 5/28/19 – 10/1/2019 | ||
Line 31: | Line 31: | ||
⦁ ROI of 7-8 years\\ | ⦁ ROI of 7-8 years\\ | ||
+ | [[https:// | ||
===== Tech Summary ===== | ===== Tech Summary ===== | ||