Line 14: Line 14:
   * Delivery on standard raised dock, no ways to lift rack out of truck if not docked   * Delivery on standard raised dock, no ways to lift rack out of truck if not docked
   * Freight Elevator and pallet jack available   * Freight Elevator and pallet jack available
 +
 +===== Network =====
 +
 +Basically ...
 +
 +  * x.y.z.255 is broadcast
 +  * x.y.z.254 is head or log in node
 +  * x.y.z.0 is gateway
 +  * x.y.z.<25 is for all switches and console ports
 +  * x.y.z.25( up to 253) is for all compute nodes
 +
 +We are planning to ingest our Dell cluster (37 nodes) and our Blue Sky Studios cluster (130 nodes) into this setup, hence the approach.
 +
 +Netmask is, finally, 255.255.0.0 (excluding public 129.133 subnet).
  
 ===== DM380G7 ===== ===== DM380G7 =====
Line 20: Line 34:
   * Dual power (one to UPS, one to utility, do later)   * Dual power (one to UPS, one to utility, do later)
  
-  * hostname [[http://www.ct.gov/dep/cwp/view.asp?A=2723&Q=325780|greentail]], another local "tail", also in reference to HP burning 18-24% more efficient in power/cooling+  * hostname [[http://www.ct.gov/dep/cwp/view.asp?A=2723&Q=325780|greentail]], another local "tail", also in reference to HP being 18-24% more efficient in power/cooling
   * eth0, provision, 192.168.102.254/255.255.0.0 (greentail-eth0, should go to better switch ProCurve 2910)   * eth0, provision, 192.168.102.254/255.255.0.0 (greentail-eth0, should go to better switch ProCurve 2910)
   * eth1, data/private, 10.10.102.254/255.255.0.0 (greentail-eth1, should go to ProCurve 2610)   * eth1, data/private, 10.10.102.254/255.255.0.0 (greentail-eth1, should go to ProCurve 2610)
   * eth2, public, 129.133.1.226/255.255.255.0 (greentail.wesleyan.edu)   * eth2, public, 129.133.1.226/255.255.255.0 (greentail.wesleyan.edu)
-  * eth3, ipmi, 10.10.103.254/255.255.0.0,  (greentail-ipmi, do later) +  * eth3, ipmi, 192.168.103.254/255.255.0.0,  (greentail-ipmi, should go to better switch ProCurve 2910, do later) 
-  * ib0, ipoib, 10.10.104.254/255.255.0.0 (greentail-ib0) +  * ib0, ipoib, 10.10.103.254/255.255.0.0 (greentail-ib0) 
-  * ib1, ipoib, 10.10.105.254/255.255.0.0 (greentail-ib1, configure, might not have cables!, split traffic across ports?)+  * ib1, ipoib, 10.10.104.254/255.255.0.0 (greentail-ib1, configure, might not have cables!, split traffic across ports?)
  
   * Raid 1 mirrored disks (2x250gb)   * Raid 1 mirrored disks (2x250gb)
Line 38: Line 52:
 [[http://h10010.www1.hp.com/wwpc/us/en/sm/WF25a/12169-304616-241493-241493-241493-4118559.html|HP Link]] (storage device) [[http://h10010.www1.hp.com/wwpc/us/en/sm/WF25a/12169-304616-241493-241493-241493-4118559.html|HP Link]] (storage device)
  
-  * Dual power (one to UPS, one to utility) +  * Dual power (one to UPS, one to utility, do later
  
   * Three volumes to start with:    * Three volumes to start with: 
Line 45: Line 59:
     * sanscratch (raid 1, no backup), 5 tb     * sanscratch (raid 1, no backup), 5 tb
  
-  * Systems Insight Manager (SIM) +  * Systems Insight Manager (SIM) [[http://h18013.www1.hp.com/products/servers/management/hpsim/index.html?jumpid=go/hpsim|HP Link]] (Linux Install and Configure Guide, and User Guide) 
-    * install, configure, monitoractions+    * Do we need a windows box (virtual) to run the Central Management Server on? 
 +    * install, configure 
 +    * requires an oracle install? nohpsmdb is installed with automatic installation (postgresql) 
 +    * linux deployment utilitiesand management agents installation 
 +    * configure managed systems, automatic discovery 
 +    * configure automatic event handling 
  
 ===== SL2x170z G6 ===== ===== SL2x170z G6 =====
Line 52: Line 72:
  
     * node names hp000, increment by 1     * node names hp000, increment by 1
-    * eth0, provision, 192.168.102.10(increment by 1)/255.255.0.0 (hp000-eth0, should go to better switch ProCurve 2910) +    * eth0, provision, 192.168.102.25(increment by 1)/255.255.0.0 (hp000-eth0, should go to better switch ProCurve 2910) 
-    * eth1, data/private, 10.10.102.10(increment by 1)/255.255.0.0 (hp000-eth1, should go to ProCurve 2610) +    * eth1, data/private, 10.10.102.25(increment by 1)/255.255.0.0 (hp000-eth1, should go to ProCurve 2610) 
-    * eth2, ipmi, 10.10.103.10(increment by 1)/255.255.0.0, (hp000-ipmi, do later) +    * eth2, ipmi, 192.168.103.25(increment by 1)/255.255.0.0, (hp000-ipmi, should go to better switch ProCurve 2910, do later) 
-    * ib0, ipoib, 10.10.104.10(increment by 1)/255.255.0.0 (hp000-ib0) +    * ib0, ipoib, 10.10.103.25(increment by 1)/255.255.0.0 (hp000-ib0) 
-    * ib1, ipoib, 10.10.105.10(increment by 1)/255.255.0.0 (hp000-ib1, configure, might not have cables!)+    * ib1, ipoib, 10.10.104.25(increment by 1)/255.255.0.0 (hp000-ib1, configure, might not have cables!)
  
     * /home mount point for home directory volume ~ 10tb     * /home mount point for home directory volume ~ 10tb
Line 81: Line 101:
   * KVM utility   * KVM utility
     * functionality     * functionality
 +
 +  * Placement
 +    * where in data center (do later), based on environmental works
  
  
 \\ \\