====== Data Center Expansion Timeline ====== ===== Assumptions ===== * Printing Operations equipment will move to Data Center * Once construction is completed it will be moved to SC523 * Jerry and Jen will move temporarily to SC519 until SC523 is renovated * Heavy construction will not begin until exams are over ===== Action Items ===== ==== Temporary Relocations during Data Center Renovations ==== ^ Action Items ^ Assigned to ^ Target Date ^ | Identify furniture to be moved from John's office | Bonnie | 4/25/06 | | Remove furniture | Bonnie | 5/2/06 | | Determine furniture to be moved into John's office | James | 4/25/06 | | Move Printing Equipment into Data Center (electricity, floor plans, etc.) | James | 5/8/06 | | Transfer phone lines to SC519 | Bonnie | 5/15/06 | | Move staff & staff furniture into SC519 | James | 5/15/06 | | Clear out Operations area completely | James | 5/17/06 | ==== Relocation of Training Program ==== ^ Action Items ^ Assigned to ^ Target Date ^ | Determine new location for training | Joanne | tbd | | Determine equipment needs | Joanne | tbd | | Determine other equipment needs | Joanne | tbd | ==== Remodeling SC523 ==== ^ Action Items ^ Assigned to ^ Target Date ^ | Determine disposition of computer equipment in SC523 | Joanne | 5/1/06| | Evaluate HVAC issues | James | 4/28/06 | | Evaluate Lighting | James | 4/28/06 | | Reassess furniture needs | James | 4/28/06 | | Assess Power and data requirements | James | 4/28/06 | | Clear out all equipment & furniture | James | tbd | ==== Data Center Construction ==== ^ Action Items ^ Assigned to ^ Target Date ^ | Meet with Mike Conte and contractors to determine construction schedule | James | 4/28/06 | | Reassess Data Center security (prox cards, temp. doors, windows and hinges, etc.) | James | 5/15/06 |