**Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | **Exley Science Center – 265 Church St. – Data Center HVAC Replacement** | ||
- | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. | + | Replace computer room air conditioning units, replace rooftop condensing units, install new economizer and pump package, install new drop ceiling and lighting, install hot and cold isle containment system. |
* Project Schedule: 5/28/19 – 10/1/2019 | * Project Schedule: 5/28/19 – 10/1/2019 | ||
Line 31: | Line 31: | ||
⦁ ROI of 7-8 years\\ | ⦁ ROI of 7-8 years\\ | ||
+ | [[https:// | ||
===== Tech Summary ===== | ===== Tech Summary ===== | ||
Line 244: | Line 245: | ||
{{: | {{: | ||
+ | ===== Sept Meetings ===== | ||
+ | |||
+ | **09/05** | ||
+ | |||
+ | New electrician but critical work coming up\\ | ||
+ | Missing one track sensor\\ | ||
+ | CARC1 installed, piping finish and leak test\\ | ||
+ | New CRAC1 power up 9/19 by Liebert with owner training\\ | ||
+ | Duct work and dampers install today\\ | ||
+ | |||
+ | **09/19** | ||
+ | |||
+ | Cancelled | ||
+ | |||
+ | ===== Sept Photos ===== | ||
+ | |||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | {{: | ||
+ | |||
+ | |||
+ | ===== The End ===== | ||
+ | |||
+ | Working with PP to see if we can do a floor tile cleaning. | ||
+ | |||
+ | Scroll up for the whole story backwards. | ||
+ | |||
+ | Commissioning happening 12/20/2019. Still to be fixed is the floor and the Ethernet cables knock outs.\\ | ||
+ | --- // | ||
**[[cluster: | **[[cluster: |