{{:cluster:100_2465_small.jpg?nolink&300|}} Vinyl doors and curtains, CRAC1 startup 10/10/2019 \\ | {{:cluster:100_2465_small.jpg?nolink&300|}} Vinyl doors and curtains, CRAC1 startup 10/10/2019 \\ |
{{:cluster:100_2467_small.jpg?nolink&300|}} Top of racks vinyl curtain \\ | {{:cluster:100_2467_small.jpg?nolink&300|}} Top of racks vinyl curtain \\ |
{{:cluster:100_2468_small.jpg?nolink&300|}} Ayi. More drilling into hot floor tiles \\ | |
{{:cluster:pp-crac2-vinyl-door.jpg?nolink&300|}} CRAC2 vinyl curtain and door \\ | {{:cluster:pp-crac2-vinyl-door.jpg?nolink&300|}} CRAC2 vinyl curtain and door \\ |
{{:cluster:pp-hot-aisle-curtain-to-crac2.jpg?nolink&300|}} West hot aisle return to CRAC units \\ | {{:cluster:pp-hot-aisle-curtain-to-crac2.jpg?nolink&300|}} West hot aisle return to CRAC units \\ |
| |
Scroll up for the whole story backwards. | Scroll up for the whole story backwards. |
| |
| Commissioning happening 12/20/2019. Still to be fixed is the floor and the Ethernet cables knock outs.\\ |