December 2006
— Steven Machuga 2007/01/31 09:34
12/9-12/10 Maintenance Packs
12/11 Database released to Upgrade Team
12/11 Tom/Uday Compile list of Issues
12/12 List of Problems released
12/19 Meeting (Uday returns to campus)
12/20
Tom will lead work on reviewing additional Wes Mods.
Uday and Barbara meet to discuss BMaps.
Afternoon Meeting Subjects
Security
Upgrade Process Review
Person Model
Data Model
Review Timelines
January
1/2 Programers continue to review and fix Wes Pages
1/2 Tom and Annette delete Daune's list of obsolete objects in Production.
-
1/9 Uday, Ed, Annette and Darrell review Job Records
1/9 Uday, Ed and Daune' review security.
1/12 Firm-up Timeline as we move forward
1/15 Primary Testers Introduction (Ed and Daune' will determine exact users).
-
1/19 Start Second Test Move.
-
-
1/29-2/9 Programmers Fix and Organize PRO1 and CUST Databases. —
Steven Machuga 2007/01/31 09:30
February 2007
— Steven Machuga 2007/01/31 09:44
2/1 Email Uday list of tasks. Currently has Payroll, Student Financials, Person Model example (needs to be defined better)
2/2 Tom and Uday create DEV and TEST databases
2/2-2/9 Programmers Fix and Organize PRO1 and CUST Databases and move fixes to DEV.
2/9 Users get first limited look at PRO1.
=== Move Plan as of 2/7/07 === — Barbara Spadaccini 2007/02/07 15:35
Wednesday 2/7
Developers will move PSUPG projects from PS89PRO1 to PS89DEV
Developers will move PL/SQL changes from PS89DEV to PS89DEV
Developers will rebuild objects as needed in PS89DEV
Friday 2/9
Uday will move 8.0 Customizations from PSPROD to PS89TST
Uday will move Content References from PS89DEV to PS89TST
Tom will move PL/SQL changes (8.9 fixes) from PS89DEV to PS89TST