hrms-sfis-upgrade:archived_schedule
Table of Contents
December 2006
— Steven Machuga 2007/01/31 09:34
- 12/9-12/10 Maintenance Packs
- 12/11 Database released to Upgrade Team
- 12/11 Tom/Uday Compile list of Issues
- 12/12 List of Problems released
- 12/19 Meeting (Uday returns to campus)
- Review PeopleSoft environment and Wes Mods
- 12/20
- Tom will lead work on reviewing additional Wes Mods.
- Uday and Barbara meet to discuss BMaps.
- Afternoon Meeting Subjects
- Security
- Upgrade Process Review
- Person Model
- Data Model
- Review Timelines
- Ed's Updated Upgrade Schedule \\stowe\HTMLDocs\Upgrade to 8.9\Current Upgrade Time Line.xls
- Additional Subjects
- Performance Tuning (deferred to later)
- Uday will develop a high level issues document.
January
- 1/2 Programers continue to review and fix Wes Pages
- 1/2 Tom and Annette delete Daune's list of obsolete objects in Production.
- 1/9 Uday at Wes Changed — Richard Langer 2007/01/05 16:54
- 1/9 Uday, Ed, Annette and Darrell review Job Records
- 1/9 Uday, Ed and Daune' review security.
- 1/12 Firm-up Timeline as we move forward
- 1/15 Primary Testers Introduction (Ed and Daune' will determine exact users).
- 1/19 Uday at Wes — Richard Langer 2007/01/16 16:13
- 1/19 Start Second Test Move.
- 1/23-1/25 Uday at Wes — Richard Langer 2007/01/16 16:13
- 1/29-1/30 Uday at Wes — Richard Langer 2007/01/16 16:13
- 1/29-2/9 Programmers Fix and Organize PRO1 and CUST Databases. — Steven Machuga 2007/01/31 09:30
February 2007
— Steven Machuga 2007/01/31 09:44
- 2/1 Email Uday list of tasks. Currently has Payroll, Student Financials, Person Model example (needs to be defined better)
- 2/2 Tom and Uday create DEV and TEST databases
- 2/2-2/9 Programmers Fix and Organize PRO1 and CUST Databases and move fixes to DEV.
- 2/9 Users get first limited look at PRO1.
=== Move Plan as of 2/7/07 === — Barbara Spadaccini 2007/02/07 15:35
- Wednesday 2/7
- Developers will move PSUPG projects from PS89PRO1 to PS89DEV
- Developers will move PL/SQL changes from PS89DEV to PS89DEV
- Developers will rebuild objects as needed in PS89DEV
- Thursday 2/8
- Steve/Tom will copy PSUPG1 to PS89TST
- Friday 2/9
- Uday will move 8.0 Customizations from PSPROD to PS89TST
- Uday will move Content References from PS89DEV to PS89TST
- Tom will move PL/SQL changes (8.9 fixes) from PS89DEV to PS89TST
- Monday 2/12
- Developers with move PSUPG projects from PS89DEV to PS89TST
- Developers will rebuild objects as needed in PS89TST
- Tuesday 2/13
- Users get first look at PS89TST
- 2/13-2/16 - Uday returns for 4 days to help users test Payroll, Student Financials and other things.